Turnkey Project : Nigeria – COLEMAN CABLE
Middle Voltage Cable Plant
Total Value: USD 9,800,000.00
Overview:




Main Products:
TYPE | CROSS SECTION |
WIRING CABLE | 1 to 5 cores 0.5—6mm2 |
WIRING CABLE | 1to 5 cores 1.5-16mm2 |
CONTROL CABLE | 2 to 19 cores 0.20—6 mm2 |
FLEXIBLE CABLE | 10~400mm2 |
CONTROL CABLE | 2 to 61 cores 0.5—240mm2 |
FLEXIBLE CABLE | 120~400mm2 |
LOW-VOLTAGE CABLE | 1 to 5 cores , 25-120mm2 ,unarmoured |
LOW-VOLTAGE CABLE | 1 to 5 cores, 150-400mm2 ,unarmoured |
AERIAL CABLE | 6.0-1000mm2 |
LOW-VOLTAGE CABLE | 1 to 5 cores, 1.5-400mm2, armoured |
MIDDLE VOLTAGE CABLE | 1 to 3 cores, 6-35KV、25-800mm2 |
Layout Design:

Supply Service List:
Service list | Quantity | Year |
The whole Solution for design; | 1 | 2012.6-2012.8 |
11KV-35KV CCV LINE(EPC PROJECT) | 2 | 2012.1 |
Stranding machine: 630/37 | 2 | 2012.1 |
Stranding machine: 630/61 | 2 | 2012.1 |
Tubular stranding machine: 630/1+6 | 2 | 2012.1 |
Tubular stranding machine: 1* 1250+12*630 1 set; | 1 | 2012.1 |
1250mm laying up machine | 1 | 2012.1 |
2500 drum twister with armoring machine | 1 | 2012.1 |
High voltage shielding room; | 1 | 2012.1 |
JTGN-50KVA/5KV/20KV AC test system | 2 | 2012.1 |
Crane: 10T; 22m | 2 | 2013-2014 |
Crane: 10T; 28m | 2 | 2013-2014 |
90 extruder machine,120+100;120+150 extruder machine | 6 | 2013-2014 |
Light and light fittings | 1000 units | 2013-2014 |
Electrical fittings | 4 containers | 2013-2014 |
Air compressor and system | 8 | 2013-2014 |
PSA Nitrogen unit | 1 | 2013-2014 |
Cooling tower and cooling water system | 5 | 2013-2014 |
Forklift: 5 tons | 2 | 2013-2014 |
Forklift: 7 tons | 2 | 2013-2014 |
Sweeper | 12 | 2014 |
Crane truck: 12 tons | 1 | 2014 |
Crane truck: 16 tons | 1 | 2014 |
Maintenance machine: lathe; drilling machine, milling machine, shaper machine | 8 | 2014 |
Woodworking machines: band saw; drilling machine | 6 | 2014 |
Shielded cables | 10 drums | 2014 |
Cable tray | 2000m | 2014 |
Loadometer: 10 tons | 2 | 2014 |
Welding machine | 100 | 2014 |
Factory fans | 200 | 2014 |
Installation tools | 6 sets | 2014 |
Project management | 12 months | 2014.1-2014.12 |
Installation | 4 months | 2014.5-2014.10 |
Commissioing and tesing | 2 months | 2014.10-2014.12 |
Training and production supervision | 2 months | 2015.1-2015.2 |